ROGER W. TITUS, District Judge.
In late 2006, AHL Development ("AHL") and Resurrection Baptist Church ("Resurrection Baptist"), entered into a contract under which AHL agreed to construct a worship facility for Resurrection Baptist at 900 Ednor Road, Silver Spring, Maryland for $994,000. Compl. ¶ 9. Around the same time, Resurrection Baptist and AHL entered into a separate contract under which AHL agreed to perform preliminary site development work for the Silver Spring facility for $429,000. Id. ¶ 7.
The parties modified the contract for site development work ("Site Development Contract") on or about March 13, 2008. Pursuant to the modification, AHL agreed to do additional site development work and the contract price was raised to $473,800. Id. ¶ 8. On or about May 2, 2008, the contract to build the worship facility ("Building Contract") was modified to increase the size of the facility. Id. ¶ 10. The amount AHL would be paid for the facility's construction was increased to $1,269,000. Id. After both the Site Development and Construction Contracts had been amended, AHL entered into a general indemnity agreement with Developers Surety and Indemnity Company ("Developers Surety") under which Developers Surety agreed to act as surety for AHL, issuing payment and performance bonds securing AHL's performance under the Building Contract. Id. ¶¶ 11-13. The bonds were issued soon thereafter, and named Resurrection Baptist and PNC Bank as co-obligees. Id. ¶ 14.
In February 2010, Resurrection Baptist declared AHL to be in default. Id. ¶ 21. As of the date of the default, the building was only 80% complete and there were insufficient contract funds to complete the project. Id. ¶ 24. Resurrection Baptist made demand against Developers Surety's performance bond to complete the facility's construction. Id. ¶ 21. Developers Surety refused this demand, asserting that Resurrection Baptist and PNC Bank materially deviated from the payment application process required under the Building Contract and made payments to AHL and its vendors without differentiating between the work that was being performed under the Building and Site Development Contracts. Id. ¶¶ 17-19. Developers Surety also claimed that Resurrection Baptist and PNC Bank failed to withhold a percentage of payments made to AHL in order to protect themselves in the event that AHL defaulted. Id. ¶ 20.
On May 14, 2010, Developers Surety initiated this action naming Resurrection Baptist and PNC Bank as defendants. Developers Surety claims that Resurrection Baptist and PNC Bank are liable for breach of contract and it seeks a declaratory judgment that its obligations under the performance and payment bonds are discharged. Id. at ¶¶ 44-45.
PNC Bank and Resurrection Baptist answered Developers Surety's complaint on
The Federal Arbitration Act (the "Act"), 9 U.S.C. § 2, states that:
The Act further provides:
9 U.S.C. § 3.
Whether this action must be stayed pending mediation and arbitration turns on the interpretation of the contracts entered into by Developers Surety, Resurrection Baptist and PNC Bank. In Maryland, contract interpretation is a question of law and contracts must be interpreted objectively. Ambling Mgmt. Co. v. University View Partners, LLC, 581 F.Supp.2d 706, 712 (D.Md.2008).
Developers Surety's claims against Resurrection Baptist and PNC Bank are based upon their alleged breach of the terms of the Building Contract. In addition to seeking damages for breach of contract, Developers Surety seeks a declaratory judgment that as a result of those alleged breaches, it has no further obligations under the payment and performance bonds it issued to secure AHL's performance. Compl. at 7-10. Whether Developers Surety's claims must be stayed pending arbitration therefore depends upon whether there is language in the Building Contract and the payment and performance bonds subjecting disputes between Developers Surety, Resurrection Baptist and PNC Bank to mandatory mediation and arbitration.
Although the payment and performance bonds contain no language compelling mediation and arbitration, they contain a clause incorporating the Building Contract between Resurrection Baptist and AHL by reference. The performance bond provides:
The payment bond contains a similar provision. Id. Ex. F. ECF No. 1-6 at 5.
The payment and performance bonds therefore incorporate the Building Contract by reference. The Building Contract contains mandatory mediation clauses which provide:
Compl. Ex. C at 31. ECF No. 1-3 (emphasis added).
The Building Contract also contains mandatory arbitration clauses which provide:
Compl. Ex. C, at 31. ECF No. 1-3.
"An agreement to arbitrate is valid, irrevocable, and enforceable, as a matter of federal law, see Moses H. Cone Memorial Hospital v. Mercury Construction Corp., 460 U.S. 1, 24, 103 S.Ct. 927, 74 L.Ed.2d 765 (1983), save upon such grounds as exist at law or in equity for the revocation of any contract. 9 U.S.C. § 2." Perry v. Thomas, 482 U.S. 483, 492 n. 9, 107 S.Ct. 2520, 96 L.Ed.2d 426 (1987) (internal quotations omitted) (emphasis added). The Federal Arbitration Act "preempts state laws which either directly contradict federal law or obstruct the realization and execution of Congressional objectives regarding the Act." Glass v. Kidder Peabody & Co., Inc., 114 F.3d 446 (4th Cir.1997).
The First, Second, Fifth, Sixth and Eleventh Circuits and several district courts have held that a surety must arbitrate disputes related to a performance bond where the performance bond specifically
In Gilbane, a case with facts similar to those presented here, the First Circuit held that a surety's counterclaim against a general contractor must be stayed pending arbitration. Commercial Union Ins. Co. v. Gilbane Bldg. Co., 992 F.2d 386, 389 (1st Cir.1993). Commercial Union Insurance Company ("Commercial Union"), the surety, issued performance bonds to secure the performance of Thames Valley Steel Corporation ("TVS"), a structural steel subcontractor, which had entered thirteen subcontracts with Gilbane, the general contractor. Id. at 386-87. TVS eventually defaulted on its obligations under the subcontracts and a dispute arose between Gilbane and Commercial Union regarding Commercial Union's obligations as surety. Id. at 387. Commercial Union filed a civil action against Gilbane alleging that Gilbane wrongfully withheld contract balances owed Commercial Union in connection with the completion of twelve of the thirteen construction projects. Id. Gilbane filed a two-count counterclaim against Commercial Union alleging breach of contract and unfair trade and claim settlement practices. Id. Commercial Union filed a reply denying liability, amended its complaint to add a count alleging Gilbane engaged in unfair and deceptive trade practices and filed two third-party complaints against other general contractors. Id. Later, Commercial Union moved to stay Gilbane's counterclaim pending arbitration, arguing that the counterclaim must be stayed because Gilbane and Commercial Union were bound by an express arbitration agreement. Id. Gilbane opposed the motion. Id.
The court noted the "strong federal policy favoring arbitration agreements, a policy which requires [the court] to resolve any doubts concerning arbitrability in favor of arbitration." Id. at 388. (internal quotations omitted). The court then held that even though the performance bond issued by Commercial Union did not contain an arbitration provision, Gilbane was required to arbitrate its counterclaim because the performance bond incorporated the TVS-Gilbane subcontract by reference, the subcontract incorporated the prime contract by reference and the prime contract contained an arbitration clause. Id. at 389. The court reasoned that the performance bond's explicit incorporation of the subcontract which explicitly incorporated the prime contract justified compelling the surety to arbitrate its claims.
Like the performance bond issued by Commercial Union to secure TVS's performance in Gilbane, the performance bond issued by Developers Surety to secure AHL's performance explicitly incorporates a construction contract that contains a mandatory arbitration provision. The primary distinction between the facts presented in Gilbane and the facts presented
The contractual language analyzed in Gilbane closely parallels the language used by the parties in this case. The arbitration provisions in the Building Contract are similar to the arbitration provision analyzed by the Gilbane court. Compare, id. at 388 ("All claims, disputes and other matters in question arising out of, or relating to this Agreement or the breach thereof,. . . shall be decided by arbitration in accordance with the Construction Industry Arbitration Rules of the American Arbitration Association then obtaining unless the parties mutually agree otherwise.") with AHL-Resurrection Baptist Building Contract §§ 4.6.1, 4.6.2. ("Any claim arising out of or related to the Contract, . . . shall. . . be subject to arbitration . . . Claims not resolved by mediation shall be decided by arbitration which, unless the parties mutually agree otherwise, shall be in accordance with the Construction Industry Arbitration Rules of the American Arbitration Association currently in effect.") Similarly, the performance bond issued by Developers Surety to secure the performance of AHL and the performance bond issued by Commercial Union in Gilbane use similar language to incorporate the underlying contract—both bonds state that the underlying construction contract is "made a part hereof." Gilbane therefore provides a close analogue to this case and supports the court's conclusion that Developers Surety is bound to arbitrate its claims. The First Circuit's reasoning and conclusion are widely shared among the federal circuits. See, Exchange Mut. Ins. Co. v. Haskell Co., 742 F.2d 274, 276 (6th Cir. 1984), United States Fidelity & Guar. Co. v. West Point Constr. Co., 837 F.2d 1507, 1508 (11th Cir.1988).
The only federal circuit to diverge from the general consensus is the Eighth Circuit.
Developers Surety argues that the performance bond it issued to secure AHL's performance similarly demonstrates that the parties contemplated resolving any disputes arising under the performance bond in legal proceedings, rather than arbitration. Pl.'s Opp'n at 5. ECF No. 16. However, the language in Developers Surety's performance bond differs materially from that used in the Mandaree bond. Unlike the Mandaree performance bond, which contained permissive language, the instant performance bond employs restrictive language. It states: "[a]ny suit under this bond must be instituted before the expiration of two (2) years from the date on which final payment under the Contract falls due." Compl., Ex. F at 3. The language in Developers Surety's bond expresses a limitation on the right to bring a suit under the bond, not an affirmation of a party's right sue. Other federal courts have held that language declaring a "statute of limitation" on claims arising under a performance bond does not negate an incorporated arbitration clause. See Cianbro Corp. v. Empresa Nacional de Ingenieria y Technologia, S.A., 697 F.Supp. 15, 18 (D.Me.1988). Absent more clear language indicating the parties' intention to resolve disputes in court, the court will not assume that the limitation on the time by which suit must be filed under the Developers Surety performance bond negates the incorporation of the arbitration clause contained in the Building Contract.
Developers Surety is also estopped from refusing to comply with the arbitration clause contained in the Building Contract. The Fourth Circuit has not specifically addressed whether a surety bond's incorporation of a contract containing a mandatory arbitration clause compels a surety to arbitrate claims arising under the incorporated contract. However, the Fourth Circuit has held in a non-surety context that a nonsignatory to a contract containing an arbitration clause can be required to arbitrate claims if it incorporated that contract by reference. See International Paper Co. v. Schwabedissen Maschinen & Anlagen GMBH, 206 F.3d 411, 417-18 (4th Cir.2000). In International Paper, the Fourth Circuit held that "a nonsignatory is estopped from refusing to comply with an arbitration clause when it receives a direct benefit from a contract containing an arbitration clause." Id. at 418. The court explained:
Id. at 419.
Here, Developers Surety asserts claims against Resurrection Baptist and PNC Bank for breach of the Building Contract, but simultaneously seeks to avoid enforcement of the arbitration clause contained in the same contract. Under International Paper, Developers Surety is equitably estopped from refusing to arbitrate its disputes with Resurrection Baptist and PNC.
Developers Surety alternatively argues that even this dispute is arbitrable, both Resurrection Baptist and PNC Bank waived their right to compel Developers Surety to arbitrate because of their pretrial participation in this lawsuit. This contention is meritless.
A party waives its right to insist on arbitration only when it "so substantially utilizes the litigation machinery that to subsequently permit arbitration would prejudice the party opposing the stay." MicroStrategy, Inc. v. Lauricia, 268 F.3d 244, 249 (4th Cir.2001). While "[d]elay in seeking arbitration is a factor to be considered when determining waiver," id. at 250, "the dispositive question is whether the party objecting to arbitration has suffered actual prejudice." Id. at 251 (emphasis in original). "Neither delay nor the filing of pleadings by the party seeking a stay will suffice, without more, to establish waiver of arbitration." Id.
Developers Surety makes no claim that it would be prejudiced by a stay, but asserts that Resurrection Baptist waived its right to insist on arbitration by answering the merits of Developers Surety's claims and asserting a counterclaim. ECF No. 16 at 6. Similarly, it argues that PNC Bank waived its right to insist on arbitration because it answered Developers Surety's complaint, filed a cross-claim, and engaged in some discovery. ECF No. 27 at 3.
As MicroStrategy makes clear, absent prejudice to the opposing party, a court will not find waiver where the parties seeking to arbitrate merely answer pleadings and engage in minimal discovery. Developers Surety has not indicated how it will be prejudiced by a stay. Resurrection Baptist filed its motion to compel arbitration contemporaneously with the filing of its answer and affirmative defenses,
For the foregoing reasons, the court holds that Developers Surety's claims are subject to the mandatory mediation and arbitration provisions and that neither Resurrection Baptist nor PNC Bank